2018 Wild Frontier Campground Expansion

Wild Frontier is adding 220 additional sites to accommodate demand from our customers. Keep an eye on this page for updates on our progress. For every entry below, new pictures will be added to the slideshow.

  • October 8th - Final north/south water mains going in on west side. Electric company doing their part for power.

  • October 4th - How about an Aerial view? Asphalt for Phase I is about 85% complete. Sod starts Friday.

  • October 3rd - ASPHALT STARTS!!!

  • September 27th Plumbing laid down to West end. Spigots, and concrete rings on East sites.

  • September 24th The trench line has made it to NW 16th Ave on the North side.

  • September 21st Check out the South Wall. It’s huge! Nice view from up top.

  • September 18th Trenching continues heading west. Electrical service panels are going in.

  • September 13th Work continues on retention area. Underground services continue going in west of Phase 1.

  • September 10th Power to the lift station.

  • September 7th HALF WAY THERE! First half of sites underground services are covered! Retention area is taking shape.

  • September 4th Lots of sand being used around the underground install. Trenching heads west again.

  • August 28th Roads and sites being prepped for surfacing.

  • August 27th Treeline between Side A and B thinned to "join" the properties. Stabilizer material for sites/roads shows up.

  • August 23rd I asked about Big Red: It scrapes dirt and relocates it. Saves hauling. Site/Road leveling still underway.

  • August 22nd Lift station is in. Trench equipment moved West along with surveyors.

  • August 20th Rough grading on the first section started. Lift station install started.

  • August 16th First fire hydrant is in. The lift station showed up. Big tractor towing two carts starting making rounds.

  • August 14th It's getting busy underground. They've completed the underground services for about 1/3 of the sites now.

  • August 13th Electrical is the big news today. Lots of wire in the ground. Water services continue heading West.

  • August 10th Fiber Optic Network conduit went in today. Trenching work for water services continues.

  • August 9th About 25 spots have wire now. Services installation continues. Two rows have water fixtures as of today.

  • August 7th The first electric wire is going in. Manholes, Storm Drains, and Water Main work is the main effort.

  • August 6th Picnic tables started showing up and check out the water services markers and lines!

  • August 3rd Some of the storm drains are placed. They're heading West along the North edge.

  • August 2nd Same type of work going on. New piles of dirt. More pipes in the ground.

  • July 31st Work continues on main water lines. Clearing is nearly complete. Constant movement right now.

  • July 30th Same as the previous update. Same work, different spot. Electrical conduit showed up today.

  • July 27th Plumbing and clearing work continues. Same view, different spot.

  • July 26th Plumbing lines are covered up on the far East side. They've moving West for more plumbing work.

  • July 24th North side clearing is nearly complete. Vertical plumbing stubs show the first site locations.

  • July 23rd Wire. 17,000lbs of it. Digging continues close to the clubhouse.

  • July 19th Busy 24 hours. Clearing continues on west side. Underground continues on east side.

  • July 17th The first plumbing is in and covered back up. Saw a bulldozer grading the westernmost street.

  • July 16th The underground crew worked hard over the weekend. Lift station is started and the first large trench is in.

  • July 13th Digging starts on the retention area. First plumbing is laid down. Clearing starts on east side.

  • July 12th Plumbing hardware makes an appearance on the property. Additional survey work.

  • July 9th Logging company begins removing salvageable trees. Scrap material is incinerated.

  • July 5th Initial interior road survey. Clearing begins.