2018 Wild Frontier Campground Expansion

Wild Frontier is adding 220 additional sites to accommodate demand from our customers. Keep an eye on this page for updates on our progress. For every entry below, new pictures will be added to the slideshow.

  • July 5th - Initial interior road survey. Clearing begins.
  • July 9th - Logging company begins removing salvageable trees. Scrap material is incinerated. 
  • July 12th - Plumbing hardware makes an appearance on the property. Additional survey work.
  • July 13th - Digging starts on the retention area. First plumbing is laid down. Clearing starts on east side.
  • July 16th - The underground crew worked hard over the weekend. Lift station is started and the first large trench is in.
  • July 17th - The first plumbing is in and covered back up. Saw a bulldozer grading the westernmost street.
  • July 19th - Busy 24 hours. Clearing continues on west side. Underground continues on east side.
  • July 23rd - Wire. 17,000lbs of it. Digging continues close to the clubhouse. 
  • July 24th - North side clearing is nearly complete. Vertical plumbing stubs show the first site locations.
  • July 26th - Plumbing lines are covered up on the far East side. They've moving West for more plumbing work.
  • July 27th - Plumbing and clearing work continues. Same view, different spot.
  • July 30th - Same as the previous update. Same work, different spot. Electrical conduit showed up today.
  • July 31st - Work continues on main water lines. Clearing is nearly complete. Constant movement right now.
  • August 2nd - Similar update - Same type of work going on. New piles of dirt. More pipes in the ground.
  • August 3rd - Some of the storm drains are placed. They're heading West along the North edge.
  • August 6th - Picnic tables started showing up and check out the water services markers and lines!
  • August 7th - The first electric wire is going in. Manholes, Storm Drains, and Water Main work is the main effort.
  • August 9th - About 25 spots have wire now. Services installation continues. Two rows have water fixtures as of today.
  • August 10th - Fiber Optic Network conduit went in today. Trenching work for water services continues.
  • August 13th - Electrical is the big news today. Lots of wire in the ground. Water services continue heading West.
  • August 14th - It's getting busy underground. They've completed the underground services for about 1/3 of the sites now.
  • August 16th - First fire hydrant is in. The lift station showed up. Big tractor towing two carts starting making rounds.